In the last year or so Neyland Stadium has had some significant upgrades.  Just a day ago news of more upgrades happening has come true.  The board of directors for UT announced the Neyland Stadium renovation project from $49 million to $337 million.  So what will the renovation be?

According to WilsonCountySource.com here is the breakdown over the next few years.

Fall 2023

  • Removal of South Stadium Hall with the structural strengthening of the stadium’s south end
  • Partially completed Wi-Fi capabilities
  • Brick cladding around in-bowl vomitories
  • New restrooms under the Gate 10 ramp

Fall 2024

  • Full stadium-wide Wi-Fi connectivity
  • Stadium kitchen, commissary, and loading dock
  • New southeast elevators vertically connecting all concourses
  • New Gate 4 entry plaza
  • Brick cladding around in-bowl vomitories (phase 2)
  • Renovations and upgrades are complete for all stadium skyboxes (see updated renderings below) 
  • Initial construction for the westside Founders Suites New restrooms and concessions on north concourse two

Fall 2025

  • Expanded south concourse 1 (increased restrooms, enhanced concessions, wider concourse)
  • Completed Founders Suites
  • Tee Martin Drive to shift south of the Gate 10 ramp

 

 